1 – Calendar
The following image displays the project schedule, with a started on January, 2019. The project ended on February 2020, practically in the expected time schedule. A Contract Change Notice (CCN) dedicated to the CRISTAL orbit followed, and ended on May 2020.
2 – Meetings
- Kick-off meeting was hold at CLS (Toulouse) in December 07, 2018.
- Project Meeting 1 was hold at CLS (Toulouse) in May 22, 2019.
- Project Meeting 2 was hold at ESTEC (Noordwijk) in October 8, 2019
- Project Meeting 3 was hold at ESTEC (Noordwijk) in February 21, 2020 (final meeting)
- Results of the orbits CCN were presented to the MAG members, by telecon, in April 24, 2020